The Lake Biwa Canal and Keage Power Station

Key points
Under 21-year-old Tanabe Sakurō, most materials were made locally and engineers were trained during the work
The First Tunnel, 2,436 m, was then the longest in Japan
Three tunnels, the Incline and the Suirokaku became the first modern civil-engineering National Treasures
With the completion of the Second Canal in 1912, it also became a source of water supply
Building the First Canal
Construction of the First Lake Biwa Canal began in 1885 (Meiji 18), and it was completed five years later in 1890, with a completion ceremony in April. Tanabe Sakurō, fresh out of the Imperial College of Engineering, was hired as civil engineer and took charge of construction.
The canal was planned by Kitagaki Kunimichi, who became the third governor of Kyoto Prefecture in 1881, to revive Kyoto, whose industries had declined and whose population had fallen after the capital moved to Tokyo in 1869 (Meiji 2). The plan was to open boat transport linking Lake Biwa and the Uji River and to build up industry by also using the water for waterwheel power, irrigation, and firefighting. The budget was initially 600,000 yen, but it swelled to 1.25 million yen after the government called for more careful construction, and a special-purpose tax on citizens was also used to fund it.
The canal was Japan's first major civil engineering project carried out entirely by Japanese, from design to construction. Under Tanabe Sakurō, who was just 21 when hired, most materials other than dynamite and cement were produced locally, and the work proceeded by training engineers at night and putting their learning into practice during the day.
The difficult First Tunnel
The First Tunnel, which carries water from Ōtsu toward Kyoto, is 2,436 m long and runs through Mount Nagara; it was then the longest tunnel in Japan. Many people doubted it would succeed, but besides digging from both sides of the mountain, workers dug a vertical shaft down from the top and tunneled out in both directions from it, the first use of this method in Japan, to speed up the work.
When it broke through, those involved are said to have become convinced the project would succeed. The tunnel portals bear stone tablets with calligraphy by Itō Hirobumi, Yamagata Aritomo, Kitagaki Kunimichi, and others.
Keage Power Station, which made electricity from water power
Keage Power Station, which uses the drop in the canal's elevation, was completed in 1891. It was Japan's first commercial hydroelectric power station.
Power generation was not part of the original plan. The biggest change to the plan came when Tanabe Sakurō and others traveled to the United States during construction to study ways of using the water, and decided to put hydroelectric power into practical use. Generation began in May 1891 (Meiji 24) with two Edison-type 80-kilowatt direct-current generators, and after repeated expansions the output reached 5,700 kilowatts in 1936 (Shōwa 11).
The electricity was used by new industries such as spinning, copper rolling, machinery, and tobacco, and in 1895 (Meiji 28) Japan's first streetcar ran from Kyoto Station to Fushimi. Ownership of the power station passed from the city to Kansai Haiden (later Kansai Electric Power) in 1942 (Shōwa 17), and a stone monument on the grounds reads "Birthplace of the Hydroelectric Power Business."
The Kamogawa Canal to Fushimi and the Canal Branch flowing north
The Lake Biwa Canal also connected toward Fushimi. Construction of the Kamogawa Canal began in 1892, and it was completed in 1894.
From Keage, the Canal Branch (Sosui Bunsen) split off and flowed north by way of Nanzen-ji, Nyakuōji, and the northeast of Mount Yoshida. When it was completed in 1890 (Meiji 23), having been started in 1887 (Meiji 20), it was about 8.4 km long, but it is now about 3.3 km. The Suirokaku aqueduct was built within the grounds of Nanzen-ji out of consideration for the surroundings along the route, which has many temples and shrines, and the walking path from Nyakuōji to Ginkakuji-michi is called the Philosopher's Path.
Route of the Lake Biwa Canal
The Second Canal and Kyoto's water supply
By the mid-1890s (the latter half of the Meiji 20s), the water volume of the First Canal could no longer meet the growing demand for electricity, and drinking water, which depended on groundwater, had also become a problem. Saigō Kikujirō, the second mayor of Kyoto City, pushed forward the "Three Great Projects": building the Second Canal, laying a water supply system, and widening roads and laying streetcar lines. Construction of the Second Canal began in 1908 (Meiji 41), and it was completed in 1912 (Meiji 45).
To protect the water source from pollution, the Second Canal was built entirely as tunnels and similar structures; it flows almost parallel to the north of the First Canal and joins it at Keage. The Keage Water Purification Plant, which began supplying water the same year, was the first in Japan to adopt rapid filtration. Even today, water supply accounts for the largest share of the canal's water use after power generation.
Water flow of the Lake Biwa Canal
| Item | Figure |
|---|---|
| Flow of the First Canal | 8.35 m³ per second |
| Flow and total length of the Second Canal | 15.3 m³ per second; about 7.4 km |
| Water sent from Lake Biwa | About 2 million m³ per day |
Heritage designations
In 1996 (Heisei 8), 12 facilities of the First Lake Biwa Canal, including the Keage Incline and the Nanzen-ji Suirokaku, were designated national historic sites. The incline is an inclined railway that bridged the roughly 36 m drop from Keage toward the Kamo River, and it is now preserved in its original form.
In August 2025 (Reiwa 7), 24 Lake Biwa Canal facilities became Important Cultural Properties. Five of them are National Treasures: the First, Second and Third Tunnels (zuidō), the Incline and the Nanzen-ji Suirokaku. They are the first modern civil-engineering structures ever to become National Treasures. The Important Cultural Properties also include the former main building of Keage Power Station (a building from 1912, Meiji 45) and the Ebisugawa Lock.
Mini quiz for this entry
Which use of the Lake Biwa Canal's water was not in the original plan but was adopted partway through construction?
What is the walking path along the Lake Biwa Canal branch from Nyakuōji to Ginkakuji-michi called?
What output had Keage Power Station, which generates power with Lake Biwa Canal water, reached by 1936 (Shōwa 11) after repeated expansions?
Sources and verification
Content checked: October 19, 2026
Updated: October 19, 2026
References are in Japanese.
